The roof will be going on the expansion portion of the project in mid-April,
with the official dry-in
of the project expected to be the later part of the month. Once that
is complete, the interior work
in the expansion will move from infrastructure to finishes, with drywall
going up and the detail
work will begin. Through all of that glass, you will see lots of activity!
In the remodeled building,
they are painting and installing ceilings, working toward the finishes
that will be installed (lighting,
carpets, new floors, etc
). While it doesnt look like we
will be able to move back into that part of
the building by the end of this semester as previously hoped, it is
looking good for us to move in
over the summer and be up and running by the start of fall semester.
We will be sure to keep you
posted on that progress.
|
When we started this project in January of 2005, 20 months seemed like
a really long time. As
we approach the remaining 6 months of construction (give or take a few
days) it is hard to recall
the original spaces and operation, all of the challenges we have faced,
and the tough decisions
required to get us to this point. We look forward to our re-opening with
great anticipation and
excitement, and hope that you will share that with us, just as you have
Watched us Grow! |